Baca Gitu Loh - Java, Indonesia - President Joko Widodo directly inspected the progress of the Jakarta Phase 2A Integrated Motorway (MRT) construction at the Monas MRT Station, Jakarta, on Friday, December 15 2023.
In his statement after the inspection, President Jokowi assessed that the Phase 2A MRT construction was progressing well and had exceeded the targets set. planned.
"So for phase 2A from the HI Roundabout to the City, the planning target of 27 percent has now reached 28.4 percent, more than the target, I think it's good," he told the media crew.
While reviewing the MRT project, President Jokowi also saw the tunnel from Monas to the Hotel Indonesia (HI) roundabout. After phase 2A is completed, the project will continue with phase 2B from Kota to Ancol.
"We just have to move on to phase 2B from Kota to Ancol," he added.
Furthermore, the Head of State targets that the MRT phase 2A will be functional by 2027. According to him, the MRT project is not an easy job because the work must be done in the midst of busy Jakarta.
"This is not an easy job because you have to work in the hustle and bustle of Jakarta and it's not easy to build tunnels, but the progress is already above target," he explained.